• June 2015 Phase II Exterior Restoration Continues
    June 2015 Phase II Exterior Restoration Continues
    August 2, 2015
    As the summer starts, the exterior roof and masonry restorations are continuing and the results are evident.
    Read More
  • May 2015
    May 2015
    June 23, 2015
    Phase II of the exterior renovation continues with the repointing of the stone mortar, removal of the top of the existing non-functioning chimney, cleaning mockups approved, replacement of the snow guards on the roof, while the May flowers continue to bloom amongst all the construction debris.
    Read More
  • April 2015
    April 2015
    May 14, 2015
    Brownstone raking of the joints commences, façade inspection survey continues, roof repairs progress, and the truss repairs are completed!
    Read More
  • March 2015
    March 2015
    March 25, 2015
    Scaffolding is completed, truss repairs continue, and masonry survey and repairs resume with the warmer weather.
    Read More
  • Mid-January/February 2015
    Mid-January/February 2015
    February 20, 2015
    Bell tower scaffolding and truss repairs continue as the pews are removed for restoration.
    Read More
  • January 2015
    January 2015
    February 5, 2015
    Handmade tools that were likely made by the blacksmith who was located on Grand Street at the time, were found in the attic during renovations. Several hand blown light bulbs were also discarded in the attic.
    Read More
  • December 2014 - Masonry & Roof Structure Repairs
    December 2014 - Masonry & Roof Structure Repairs
    January 15, 2015
    Scaffolding continues to envelop the Cathedral to facilitate the roofing and masonry repairs. Simultaneously, the attic is cleared from debris to facilitate the truss reinforcement repairs.
    Read More
  • Fall 2014 Work Begins!
    Fall 2014 Work Begins!
    November 5, 2014
    After much anticipation and hard work, the scaffolding is being erected on the entire exterior of the Cathedral in order to inspect and repair the masonry and roofs.
    Read More
  • PLANNING STAGE
    PLANNING STAGE
    October 1, 2014
    During the design process, further investigations and exploratory work was required to assess the existing conditions and reveal the life safety hazards that needed to be rectified.
    Read More
  • Securing Priceless Treasures
    Securing Priceless Treasures
    September 17, 2013
    The Cathedral is full of many priceless treasures which were in danger of being damaged if any more ceiling tiles were to fall. These treasures have been removed and stored in a secure location offsite.
    Read More
  • Pre-Construction Stage
    Pre-Construction Stage
    May 12, 2013
    A complete building inspection was made after the Cathedral was closed down due to the unsafe ceiling conditions. Included in this update are photos of damaged areas which require life safety and interrelated renovations.
    Read More